The Challenge
A critical pre-cast concrete Z wall platform installation was scheduled for the Northumberland line project at Northumberland Park Station. The tight deadline of a 54-hour possession window presented a significant challenge, demanding meticulous planning and flawless execution.
The Solution
LGH swiftly moved and delivered the following equipment to the site the same day:
Lifting shackle spherical head
Chain slings with shortening clutches and safety hooks
The Outcome
Despite the demanding timeline and complex logistics, LGH's provided essential equipment to ensure the successful completion of the Z wall platform installation. The project was delivered on schedule, paving the way for subsequent construction phases.